Chrome has dropped XSLT. What breaks in InterSystems, and the fixed build for your version
Chrome stopped running XSLT on 17 November 2026, and Edge follows in December. On unfixed builds, the InterSystems Message Viewer and Visual Trace no longer show XML properly. Every IRIS line now has a fixed build, 2026.3.0 included. We list each one, the browser policy that covers the gap, and why Caché sites should start planning the IRIS move.
part 23 of 53 · Platform releases, explained from scratchthe ideaChrome cut XSLT on 17 November. Most InterSystems fixes beat it, one came a day late
after reading, you can- Spot which InterSystems screens break when the browser drops XSLT, and which release line you're on
- Pick the fixed build for your line, and set the XSLTEnabled policy where the fix lands late
- Plan the Caché or Ensemble move to IRIS before maintenance releases stop in March 2027
Chrome 158 stopped running XSLTdefinitionA way to turn raw XML into a page someone can actually read. Browsers have done it for years. Chrome and Edge are taking it out now, mostly for security reasons. on 17 November 2026, so unfixed InterSystems builds can't show XML properly in Message ViewerdefinitionThe Management Portal screen your integration staff use to look up a single message. It's where they check what actually went through a production. or Visual TracedefinitionIt draws one message's path through a production, step by step. When an interface misbehaves, this is where engineers go to see which step it reached and what it said there.. Your interfaces keep running. Every IRIS line now has a fixed build, ending with 2026.3.0 on 18 November. HealthShare's fix still has no release notice, and Edge follows in the week of 10 December. If you're still on Caché or Ensemble, treat 2018.1.13 as one of the last fixes before maintenance releases end on 31 March 2027.
Your browser has dropped a feature the InterSystems admin screens lean on
InterSystems IRIS, HealthShare and the older Caché and Ensemble sit in a lot of hospitals and health plans, passing HL7 and other messages between clinical systems. Integration staff watch that traffic in a web page called the Management Portal. Some of its screens send raw XML to the browser along with a stylesheet, and the browser turns it into a readable page. That conversion step is called XSLT. Google has taken it out of Chrome for security reasons, and Microsoft is doing the same in Edge. Once the browser drops it, those screens can't draw the message the way they used to. Nothing happens to the messages themselves. What breaks is your team's view of them.
It's like a mailroom whose franking machine breaks. Letters still get delivered, but each one arrives as a bare sheet of code, and someone has to decode it by hand before anyone knows what it says.
- Teams on IRIS or IRIS for Health
- HealthShare and Health Connect sites
- TrakCare and EMPI users
- Anyone still on Caché or Ensemble
- Desktop teams who manage Chrome or Edge
Why it matters to you
When an interface fails overnight, the on-call engineer opens Visual Trace, finds the message and reads it. If that page can't render, they're stuck working from raw XML or exports. Every incident takes longer, and so does every audit query about what a message contained.
InterSystems rated the operational risk High in its 21 October advisory, DP-456155, and we'd agree. Nobody's data leaks and nothing's lost. Still, a hospital's integration team loses its main window into live traffic on the day a routine browser update arrives, and that hurts during an outage.
The list of affected products is long. InterSystems names IRIS, IRIS for Health, Health Connect, EMPI, TrakCare and most of the HealthShare family, from Unified Care Record to Provider Directory. It also says it's still checking the full scope, so expect that list to grow.
-
01 Engineer opens a message
Someone on the integration team clicks a message in Message Viewer or Visual Trace. It's how they check what an interface actually sent.
-
02 Portal sends XML
The server sends the message as XML, with a note naming the stylesheet the browser should apply. The browser's meant to do the rest.
-
03 Browser used to format it
Until now Chrome and Edge ran that stylesheet and showed a readable, laid-out page.
-
04 From Chrome 158 it can't
The browser won't run the stylesheet any more. So the engineer's looking at unformatted XML, or a page that doesn't show the message properly.
-
05 Fixed build renders it again
The fixed builds for your line address this alert. Once they're in, the screen shows the message properly again after the browser change.
For engineers: Chrome is removing both the XSLTProcessor JavaScript class and the xml-stylesheet processing instruction when it points at an XSLT file. An xml-stylesheet that points at CSS still works. Google's reasons are security and low use. It cites memory-safety bugs in libxslt and puts XSLT at about 0.02% of page loads. Firefox and WebKit have said they plan to remove it too, so switching browsers won't save you for long.
What InterSystems fixed, and which build you need
The fix lands differently on each release line
Both came out on 28 October for IRIS, IRIS for Health and Health Connect. If you run either line, this is the build to test first. Newer .7 builds followed on 18 November, but their release post doesn't mention this alert, so ask the WRC before you pick .7 instead.
The advisory planned the HealthShare fix in HS 2026.2 for 29 October. We still couldn't find a release notice on 19 November, so check with InterSystems that it's out for your products before you plan around it.
Both came out on 12 November as planned, five days before Chrome 158. 2018.1.13 covers Caché, Ensemble and Health Connect on the 2018.1 line.
It went GA on 18 November, the day after Chrome 158, as build 2026.3.0.212.0. There's no fixed 2026.2 build, so if you run 2026.2 this is your upgrade.
InterSystems said in 2023 it plans Caché maintenance releases only for Windows and Red Hat. macOS stopped at 2018.1.9, so ask before you count on 2018.1.13 anywhere else.
Chrome 158 switched it off on Stable on 17 November. Edge users get a few more weeks, since Microsoft lists the change for Edge 159.
Most sites on an Extended MaintenancedefinitionInterSystems' slower release track, the one 2025.1 and 2026.1 sit on. These lines keep getting maintenance builds for years, so they usually get fixes like this one first. release have an easy path. If you're on 2025.1 or 2026.1, take the .6 maintenance build, test your productions on it and roll it out. It's a maintenance release on the line you already run, so it's a much smaller job than a version upgrade.
The awkward spots were at the edges. 2024.1 and Caché sites got their fix on 12 November, five days before Chrome changed, which left little time to test. Sites on the 2026.2 Continuous Delivery track had to wait for 2026.3.0, which came out a day after Chrome. If either group hasn't upgraded yet, set up the browser policy described below as a bridge.
| Release line you run | Fixed build | Date | What to do |
|---|---|---|---|
| IRIS, IRIS for Health, Health Connect 2026.1 | 2026.1.6 (2026.1.6.627.0) | Released 28 Oct 2026 | Test and deploy now |
| IRIS, IRIS for Health, Health Connect 2025.1 | 2025.1.6 (2025.1.6.814.0) | Released 28 Oct 2026 | Test and deploy now |
| HealthShare | HS 2026.2 | Planned 29 Oct 2026, no release notice yet | Ask the WRC, bridge with the policy |
| IRIS, IRIS for Health, Health Connect 2024.1 | 2024.1.7 (2024.1.7.1007.0) | Released 12 Nov 2026 | Test and deploy now |
| Caché or Ensemble 2018.1 | 2018.1.13 | Released 12 Nov 2026 | Deploy now, plan the IRIS move |
| 2026.2 (Continuous Delivery) | 2026.3.0 (2026.3.0.212.0) | Released 18 Nov 2026 | Upgrade, bridge with the policy until then |
The dates so far, and the ones still ahead
- 21 Oct 2026InterSystems advisory
DP-456155 goes out with the list of affected products and planned fixes.
- 28 Oct 20262026.1.6 and 2025.1.6
The first fixed builds come out for IRIS, IRIS for Health and Health Connect.
- 12 Nov 20262024.1.7 and 2018.1.13 out
The fixes for 2024.1 and for Caché and Ensemble arrived on the planned date, five days before Chrome's change.
- 17 Nov 2026Chrome 158
Chrome Stable stopped running XSLT unless the enterprise policy keeps it on. Unpatched portals stop rendering messages on machines without it.
- 18 Nov 20262026.3.0 out
The Continuous Delivery fix arrived a day after Chrome's change, as build 2026.3.0.212.0. Teams still on 2026.2 need the policy until they upgrade.
- Week of 10 DecEdge 159
This is the release where Microsoft lists the XSLT change, about three weeks after Chrome. If you're on Extended Stable, it comes with 160 in the week of 7 January.
- 31 Mar 2027Caché maintenance ends
InterSystems plans no Caché or Ensemble maintenance releases after this. Future problems won't get a new build.
- 17 Aug 2027Chrome 176
The XSLTEnabled policy stops working and XSLT is gone for everyone. Edge plans the same at 176.
Keep your engineers' screens working while the patch waits its turn
Chrome and Edge both have an enterprise policy called XSLTEnableddefinitionAn enterprise browser policy in Chrome and Edge. Set it on and XSLT keeps working on managed machines until version 176.. Set it to on and XSLT keeps working on managed machines, whatever the browser's default is. Google says the policy stops working in Chrome 176, on 17 August 2027, and Microsoft plans the same for Edge 176. InterSystems' advisory doesn't mention it, but both browser makers document it for exactly this kind of transition.
We'd use it as a bridge on the machines your integration and support staff use, and nowhere else. Browsers keep patching, the portal keeps rendering, and you get to install the InterSystems fix in a normal change window instead of rushing it. Turn it off again once every instance those people log into is on a fixed build.
For one machine, the setting is a DWORD called XSLTEnabled with the value 1, under the Edge or Chrome policy key in the registry. Microsoft's support article gives the exact commands. For a fleet, push it through Group Policy or Intune, then check it shows up at edge://policy or chrome://policy after a browser restart.
Microsoft also suggests the opposite test, and we'd run it now. Set XSLTEnabled to disabled on one test machine and click through the Management Portal, Zen Reports and anything else your teams open in a browser. Whatever breaks on that machine is what breaks for everyone without the policy. It catches more than InterSystems screens. Microsoft has already said its own RD Web Access page fails when XSLT is off.
- Chrome 158 is reaching desktops now, and Edge 159 follows in December. Unpatched instances without the policy lose Message Viewer and Visual Trace
- On-call staff end up reading raw XML in the middle of an incident. Every fix takes longer
- Someone panics and pauses browser updates. The security fixes get held back along with everything else
- The InterSystems upgrade still has to happen, now under pressure
- You test the fixed build for your line and roll it out. It goes in a normal change window, with no rush
- Sites still waiting for a fix turn XSLTEnabled on for admin machines. Nobody loses their view while the patch waits for a change window
- Your desktop team keeps pushing browser updates as usual. The portal works and the security fixes still land
- One test machine with XSLT switched off shows you every other app that still needs it. You find out now instead of during an outage
Today: the browser does the formatting
The portal sends XML plus a stylesheet, and Chrome or Edge turns it into the page your engineers read.
After the fix: the browser just shows a page
Once the fixed build is in, the portal keeps rendering after the browser change. Machines whose instance isn't patched yet lean on the policy for now.
Caché and Ensemble get one more fix, and then the builds stop
If you're still on Caché or Ensemble, 2018.1.13 is the release you need for this problem. It's also one of the last you'll get. InterSystems said in 2023 that no Caché or Ensemble maintenance releases are planned after 31 March 2027. It hasn't set an end date for support, so you can still open a case. But there won't be new builds for the next browser change or the next security flaw.
This advisory shows what that looks like in practice. A change outside InterSystems' control broke the product, and the fix came as a maintenance release. After March there's no next maintenance release to carry it. Some sites are already there. InterSystems said in 2023 it doesn't plan Caché maintenance releases outside Windows and Red Hat, and macOS stopped at 2018.1.9. If you run anything else, check with InterSystems before you count on 2018.1.13.
Use the 2018.1.13 rollout as your rehearsal for the IRIS move. You'll inventory instances, test productions and plan a change window anyway. Write down how long each step takes and what broke. That's most of the information an IRIS migration plan needs, gathered while you're doing work you have to do regardless.
The patch path, from inventory to rollout
- 01List every instance and its build
Write down the product, release line and exact build for every IRIS, HealthShare, Caché and Ensemble instance, test ones included. The build decides which row of the fix table you're on.
- 02Find who opens the portal
List the people and machines that use Message Viewer, Visual Trace, Zen Reports or TrakCare referral documents. Those are the machines that need the bridge policy if a fix runs late.
- 03Test with XSLT off
Set XSLTEnabled to disabled on one test machine and click through those screens. Note every page that breaks, InterSystems or not.
- 04Set the bridge where needed
Until your 2024.1, Caché, 2026.2 or HealthShare instances are on their fixed build, push XSLTEnabled on to the admin machines. Note the date so someone takes it off later.
- 05Patch test, then production
Install the fixed build on a test instance, run your regression messages through the productions and check the screens render with XSLT off. Then roll it to production in a normal change window.
- 06Remove the bridge
Once every instance those staff use is fixed, turn the policy off again. Chrome and Edge drop it at version 176 anyway.
What to do now
What to do, by who you are
- Ask one question: which InterSystems products and versions do we run, and is any of it 2024.1, 2026.2, Caché or Ensemble?
- Approve the fixed build for your line as planned work this month. On 2025.1, 2026.1, 2024.1 or Caché it's a routine patch on the line you already run.
- If anything runs Caché or Ensemble, put the IRIS migration on next year's budget now. No Caché or Ensemble maintenance releases are planned after 31 March 2027.
- Write down the exact build of every instance, test ones included, and find its row in the fix table. That row tells you which plan you're on.
- Put the fixed build on a test instance and push your regression messages through every production. You want problems to show up there, not in the live portal.
- Ask the WRC whether HS 2026.2 is out for your HealthShare products. We still can't find a release notice for it.
- Set XSLTEnabled to disabled on one test machine and hand it to the integration team for a day.
- Prepare an XSLTEnabled-on policy for the admin group, ready to push if a fix runs late.
- Don't pause browser updates for this. The policy keeps XSLT without giving up security fixes.
- Write the XSLTEnabled exception down, with an owner and an end date. It stops working in August 2027 whatever you do, so somebody has to remove it before then.
- From 1 April 2027, log every Caché or Ensemble instance on the risk register as getting no more maintenance releases. Put the migration plan next to it, because auditors will ask.
Make the next browser change hurt less
Durable fixes that come out of this one
- 01Stay on a maintained release line
The fix reached 2025.1 and 2026.1 first, a week after the advisory. Sites on 2024.1 and Caché waited until five days before Chrome changed, with almost no time to test. Being on a maintained line got people the fix weeks earlier.
- 02Keep a regression message pack
A saved set of test messages per production turns a maintenance upgrade into a test run. Without one, every patch becomes a project.
- 03Give admins a managed browser profile
Put integration staff in their own browser policy group. When the next change lands, you can bridge or test that group without touching the whole hospital.
- 04Watch the browser roadmaps
Chrome and Edge publish their removals months ahead. Google published this timeline in October 2025, more than a year before the cutoff. Somebody just has to be reading it.
If it goes wrong
Chrome updated and nobody can read the messages? Start here and work down
Your interfaces are almost certainly still running. This is a display problem, so the goal is to give engineers back a readable view fast, then fix it properly in a planned change.
- 01Containfirst hour
- Confirm the productions are still processing. Check queue counts and error logs, which don't depend on browser XSLT.
- Point on-call staff at View XML Source on the Message Viewer pages. It's slow to read, but it works until the screens are back.
- 02Restore the viewfirst hours
- Push XSLTEnabled on to the integration team's machines through Group Policy or Intune, then restart their browsers.
- Open chrome://policy or edge://policy and check the setting is there. Then open a message and make sure it renders.
- 03Fix properlyfirst weeks
- Install the fixed build for your line in a normal change window, after a regression run on a test instance.
- Teams on 2026.2 have to plan the move up to 2026.3.0. On Caché or Ensemble, put 2018.1.13 on and start the IRIS plan while it's fresh.
- 04Recover and learnafter the fix
- Turn XSLTEnabled off again once every instance those staff use is fixed.
- Give whoever owns your InterSystems upgrades the Chrome and Edge roadmaps to watch. The next removal will be announced months ahead too.
What it looks like in real estates
Three InterSystems setups you'll probably recognise, and what we'd do in each
- the setup
- A regional hospital runs its HL7 interfaces on Health Connect 2025.1. Every desktop has Chrome, updating on its own, and the integration team spends its day in Visual Trace.
- what happens
- Chrome 158 is out, and their desktops update on their own. Any machine that gets it before the hospital patches loses the Visual Trace view, so every interface error takes longer to track down.
- what to do
- Install 2025.1.6 on the test instance now, run the regression messages, and roll it out in the next change window. Push XSLTEnabled to the integration team's machines until it's in.
- the setup
- A payer runs claims and eligibility feeds on Ensemble 2018.1 on Windows. A migration to IRIS has been on the list for two years without a date.
- what happens
- The 2018.1.13 fix came out on 12 November, so the team had only a few days to test it before Chrome changed. After March 2027 nobody gets another Ensemble maintenance release, and the migration still has no date.
- what to do
- Push XSLTEnabled on to the admin machines now, install 2018.1.13 in the next change window, and use that rollout to size the IRIS migration.
- the setup
- A digital health team chose IRIS for Health 2026.2 to get at the new FHIR features early. Everyone's in Edge, and IT pushes browser updates to their laptops.
- what happens
- There's no fixed 2026.2 build. 2026.3.0 came out on 18 November, and Edge 159, where Microsoft lists the XSLT change, is due in the week of 10 December.
- what to do
- Plan the 2026.3.0 upgrade for late November and keep XSLTEnabled ready to push in case it slips past Edge 159.
How Cohash helps
We patch and upgrade InterSystems IRIS and HealthShare, and we move Caché and Ensemble to IRIS. For this change we'd start with an inventory of every instance and build, test the fixed release against your productions on a copy, and set up the browser bridge for the machines that need it. Read more on our InterSystems page, ask about InterSystems engineers, or book an assessment if you'd like the version check done for you.
What to take from this
- 01
Chrome 158 stopped running XSLT on 17 November, and Edge 159 follows in the week of 10 December. Message Viewer and Visual Trace stop rendering XML properly on unfixed builds.
- 02
If you run 2025.1 or 2026.1, you're in the easy group. Install the .6 build, which has been out since 28 October, after a test run.
- 03
2024.1 and Caché got their fix on 12 November, and 2026.2 sites move up to 2026.3.0, out since 18 November. HealthShare's fix still isn't confirmed. Until you've patched, push the XSLTEnabled policy to admin machines so nobody's left reading raw XML.
- 04
Don't hold browser updates to dodge this. The policy keeps XSLT working until version 176 without giving up security fixes.
- 05
Caché and Ensemble get no maintenance releases after 31 March 2027. Use the 2018.1.13 rollout to size the IRIS move.
01Will the Chrome XSLT removal stop my InterSystems interfaces?
No. InterSystems says the XML data isn't changed and only browser-side display is affected. Productions keep sending and receiving messages. What stops working is how Message Viewer, Visual Trace and some other screens show XML content.
02Which InterSystems build fixes the XSLT problem?
It depends on the line you run. 2026.1.6 and 2025.1.6 came out on 28 October, 2024.1.7 and Caché 2018.1.13 on 12 November, and 2026.3.0 on 18 November for the Continuous Delivery track. HealthShare's fix was planned in HS 2026.2, and we still can't find a release notice. The table above has every row.
03When does Edge stop supporting XSLT?
Microsoft puts the XSLT change in Edge 159, due on Stable in the week of 10 December 2026, and in 157 for its preview channels. InterSystems' advisory lumps Chrome and Edge together under 17 November. Treat Edge's extra weeks as slack, not a reason to wait.
04Can we keep XSLT working in the browser for a while?
Yes, on machines you manage. Turn the XSLTEnabled policy on in Chrome or Edge through Group Policy, Intune or the registry, and XSLT keeps working there until version 176. Chrome puts that at 17 August 2027. We'd treat it as a bridge to the fixed build, and take it off once the patch is in.
05Should we block Chrome and Edge updates instead?
We wouldn't. InterSystems lists it as a last resort and tells you to weigh the security impact first. Holding updates leaves every browser without its security fixes. The XSLTEnabled policy gets you the same result and keeps browsers patched.
06Is Caché still supported after March 2027?
InterSystems hasn't set an end date for Caché or Ensemble support, so you can still raise cases. But it plans no maintenance releases after 31 March 2027, so there won't be new builds for future problems like this one. macOS stopped at 2018.1.9.
07We're on IRIS 2026.2. Is there a fix for us?
Yes, by moving up. InterSystems didn't list a fixed 2026.2 build. The Continuous Delivery fix is 2026.3.0, which came out on 18 November as build 2026.3.0.212.0. Plan that upgrade and keep the browser policy on the admin machines until it's done.
08Has HealthShare released the XSLT fix?
InterSystems planned the HealthShare fix in the HS 2026.2 product versions for 29 October. We still couldn't find a release notice on 19 November. Ask the WRC whether HS 2026.2 is out for your products, and keep XSLTEnabled on for HealthShare admins until you've installed it.
09Is InterSystems IRIS 2026.3 out?
Yes, InterSystems put it out on 18 November as build 2026.3.0.212.0. It is a Continuous Delivery release, and the advisory names it as the XSLT fix for anyone on 2026.2. Check who holds %Development before you upgrade. The upgrade quietly adds six new resources to those roles, so someone should review them.
Three questions, about a minute
Pick an answer and we'll tell you if it's right, and why it is or isn't. The score stays in this browser.
-
Q1Your interfaces run on Health Connect 2026.1, and nobody controls when Chrome updates. What would you do now?
show the answer
B. Test the 2026.1.6 build, then install it in a change window 2026.1.6 came out on 28 October with the fix, and it's a maintenance build on the line they already run. Blocking updates trades away security fixes, and Firefox has said it plans to drop XSLT too.
-
Q2A payer on Ensemble 2018.1 can't install 2018.1.13 until early December. How do they keep the portal readable until then?
show the answer
A. Push XSLTEnabled on to the admin machines' browsers The policy keeps browser XSLT working on managed machines until version 176, so engineers keep their view while the fix waits for a change window. Messages are fine, but staff still need to read them.
-
Q3A Caché site is about to install 2018.1.13. Why should that rollout also start a bigger conversation?
show the answer
C. No new Caché build is planned after 31 March 2027 to carry a fix like this After March there's no next maintenance release to carry a fix like this one. Support cases continue, but new builds don't, and macOS stopped at 2018.1.9 already.