delivered for clients · names withheldimplementation Security operations

OT security baseline for plants and pipelines

Cohash sets an OT security baseline for plants, substations and pipeline sites. We trace switches and place passive sensors from Claroty, Nozomi Networks or Dragos, build an asset inventory, group assets into ISA/IEC 62443 zones and conduits, put vendor remote access through one recorded path, and connect OT alerts to your SOC with playbooks that say when to call the plant.

  1. 01Site walk and switch trace
  2. 02Passive inventory and baseline
  3. 03Zones and conduits
  4. 04Remote access and accounts
  5. 05SOC integration
case-study / ot-security-baseline delivered
beforeFlat plant networks with no current OT inventory afterMonitored zones and conduits (Claroty, Nozomi, Dragos)
01 · REMOTE ACCESS 02 · INDUSTRIAL DMZ 03 · PLANT ZONES 04 · SECURITY OPERATIONS Vendor engineers: OEM and integrator support Vendor engineers OEM and integratorsupport Brokered remote access: MFA · session recording Brokered remoteaccess MFA · sessionrecording Conduit firewalls: IEC 62443 conduits Conduit firewalls IEC 62443 conduits OT sensor console: Claroty · Nozomi · Dragos OT sensor console Claroty · Nozomi ·Dragos Control zones: PLCs · RTUs · HMIs Control zones PLCs · RTUs · HMIs Passive sensors: SPAN and TAP points Passive sensors SPAN and TAP points SIEM: OT alerts SIEM OT alerts CMDB: OT asset records CMDB OT asset records SOC playbooks: when to call the plant SOC playbooks when to call the plant
case file

The story

Told without the client's name or anything that could identify them.

what happened

A pipeline operator's security team couldn't say how many PLCs, RTUs and HMIs ran at each site, and vendor engineers reached controllers through a shared remote desktop account. TSA's pipeline directive still requires segmentation, access control and continuous monitoring, and an insurer had asked for a zones and conduits diagram that didn't exist. We walked pilot sites with controls engineers, traced switch topology by Purdue level and placed passive sensors at agreed SPAN and TAP points. The sites ended up with an asset inventory, IEC 62443 zones and conduits enforced by firewall rules, one recorded path for vendor access, and SOC playbooks that say when to call the plant.

why it was urgent

The rules haven't loosened. TSA's revision 02G of its pipeline security directive, posted on 1 May 2026, still requires segmentation, access control, continuous monitoring and risk-based patching. FERC approved NERC CIP-015-1 on internal network security monitoring in June 2025. And on the vendor side, Mitsubishi Electric completed its Nozomi Networks acquisition on 28 January 2026.

problem statement
  • openNobody can say how many PLCs, RTUs and HMIs run at each site.
  • recurringVendor engineers reach controllers through a shared remote desktop account.
  • blockedAn insurer or regulator asked for zones and conduits and there is no diagram.
  • openOT alerts reach the SOC, but analysts have no playbook for them.
architecture

The estate, before and after

before
before

Before: flat plant networks and shared vendor access

Vendor engineers reached controllers on a flat plant network through one shared remote desktop account with no recording. The SOC saw occasional OT alerts with no playbook and no inventory to look them up in.

Before: flat plant networks and shared vendor access Vendor engineers reached controllers on a flat plant network through one shared remote desktop account with no recording. The SOC saw occasional OT alerts with no playbook and no inventory to look them up in. 01 · REMOTE ACCESS 02 · PLANT NETWORK 03 · SECURITY OPERATIONS remote desktop direct access unsegmented occasional alerts triage Vendor engineers OEM and integrator support Shared remote desktop one account · no recording Flat plant network no zones · no currentinventory PLCs count unknown per site SOC analysts no OT playbook SIEM IT alerts
Read the diagram as text
  1. Vendor engineers → Shared remote desktop: remote desktop
  2. Shared remote desktop → Flat plant network: direct access
  3. Flat plant network → PLCs: unsegmented
  4. Flat plant network → SIEM: occasional alerts
  5. SIEM → SOC analysts: triage
after
after

After: monitored zones, conduits and one vendor path

Vendors can only reach a control zone through a brokered, recorded path and the conduit firewalls. On the monitoring side, passive sensors feed an OT console that pushes alerts to the SIEM and assets to the CMDB, where SOC playbooks pick them up.

After: monitored zones, conduits and one vendor path Vendors can only reach a control zone through a brokered, recorded path and the conduit firewalls. On the monitoring side, passive sensors feed an OT console that pushes alerts to the SIEM and assets to the CMDB, where SOC playbooks pick them up. 01 · REMOTE ACCESS 02 · INDUSTRIAL DMZ 03 · PLANT ZONES 04 · SECURITY OPERATIONS MFA sign-in recorded session allowed conduit mirrored traffic assets and alerts alerts assets triage Vendor engineers OEM and integrator support CA Brokered remoteaccess MFA · sessionrecording Conduit firewalls IEC 62443 conduits OT OT sensor console Claroty · Nozomi ·Dragos Control zones PLCs · RTUs · HMIs OT Passive sensors SPAN and TAP points SIEM OT alerts SE CMDB OT asset records SOC playbooks when to call the plant
Read the diagram as text
  1. Vendor engineers → Brokered remote access: MFA sign-in
  2. Brokered remote access → Conduit firewalls: recorded session
  3. Conduit firewalls → Control zones: allowed conduit
  4. Control zones → Passive sensors: mirrored traffic
  5. Passive sensors → OT sensor console: assets and alerts
  6. OT sensor console → SIEM: alerts
  7. OT sensor console → CMDB: assets
  8. SIEM → SOC playbooks: triage
results

What the client got

What changed for the client once the work was done. Described, not scored: we don't publish client figures.

  1. result 01

    Every pilot site has a current asset inventory

    Controllers, HMIs and other assets are listed by passive sensors and a central console, with protocols and communication paths. We baselined them through a normal production week and a maintenance window.

  2. result 02

    Zones and conduits are enforced by firewall rules

    Zones and conduits follow IEC 62443-3-2. Target security levels were set with the operator's engineers, and firewall rules were written to match.

  3. result 03

    Vendor access goes through one recorded path with MFA

    Vendors and engineers get one brokered way in, with MFA and session recording. We inventoried the shared and default accounts on field equipment and brought them under control.

  4. result 04

    SOC analysts know when to call the plant

    OT alerts land in the SIEM, assets in the CMDB. Playbooks tell analysts when to call the plant rather than isolate a host that runs the process.

  5. result 05

    Alerts are tuned with plant staff

    Plant staff went through every baseline alert with us. What's left are alerts operators recognize and will act on.

what can go wrong

Risks we plan for

  1. Sensors in the wrong place

    One sensor on the plant core switch misses traffic that stays inside cell switches. Placement follows the switch trace, not the org chart.

  2. SPAN load on old switches

    Older managed switches can choke when you mirror traffic off them. Where load is high, we plan TAPs or staged mirroring.

  3. Active scanning near controllers

    Some field devices fall over when you poll them. So active queries stay off unless plant engineers sign off on the scope and timing.

  4. Baselines nobody tunes

    Untuned alerts get ignored within weeks. Tuning is part of the work, with plant staff in the review.

ai in this move

Where AI helps, and where it needs guardrails

Where an OT platform offers an AI assistant for alert triage or asset context, check what data leaves the site, and where it is processed, before turning it on. AI agents never get a write path into levels 0 to 2. At most, analysts get a read-only MCP tool over the asset inventory or historian data in the industrial DMZ, with its own identity and logs.

forward deployed engineers →
you keep

What you're left with

We write these for your setup, and they're working documents. Your team should be able to keep things running from them long after we've gone.

  • plan01

    Switch trace and SPAN/TAP plan per site

    yours to keep
  • inventory02

    OT asset inventory with protocols and communication paths

    yours to keep
  • design03

    IEC 62443 zone and conduit diagram with target security levels

    yours to keep
  • design04

    Vendor remote access design with session recording

    yours to keep
  • runbook05

    SOC playbooks for OT alerts

    yours to keep
talent and delivery · monitored zones and conduits (claroty, nozomi, dragos)

Certified engineers, wherever you need them.

Some clients want a project team, some want a couple of engineers on theirs. Either works. Onsite, nearshore or offshore, with handovers across time zones that keep things moving.

Onsite

Engineers at your sites in the US

Nearshore

Overlapping hours with US teams

Offshore

Overnight progress on your backlog

All time zones

Coverage handed over across time zones

24-hour coverage · US Central time
OnsiteUS business hours
Nearshoreoverlapping US hours
Offshoreovernight progress
Combinedhandover, not hand-off
01Does passive monitoring put the process at risk?

Passive sensors read mirrored traffic and send nothing to controllers. The risks are switch load on old hardware and active polling if you enable it, and we check both with plant engineers first.

02Claroty, Nozomi Networks or Dragos?

It depends on your control vendors' protocols, your site layout and who will run the platform. We test two on your own mirrored traffic at one site before you buy.

03Does this satisfy TSA or NERC CIP?

You get the inventory, segmentation, access control and monitoring evidence those rules ask for. Whether that meets a specific requirement is your compliance team's and your regulator's decision.

04How many sites can we do at once?

It depends on site size, travel and how much plant staff time is available. Most programs prove the pattern at one or two sites, then roll out the rest.

next step

Planning this move?

A 30-minute working session with a senior engineer. No slides.

useful to bring
  • The platform and the version you're on
  • Where you need to get to, and by when
  • What's custom: rules, plugins, integrations
  • Any audit finding or deadline driving it